A contractor asks a town where payment applications should be sent. By when must the town have identified the office or employee that receives them?
Correct Answer
A) Within 10 days after contract award or notice to proceed
Section 218.735(1) requires the local governmental entity to identify the agent, employee, facility or office to which the contractor may submit its payment request, either in the contract or by separate written notice no later than 10 days after the contract award or notice to proceed. The identification matters because submission to that office is what starts the payment clock.
Why This Is the Correct Answer
Section 218.735(1) requires the local governmental entity to identify the agent, employee, facility or office to which the contractor may submit its payment request, either in the contract or by separate written notice no later than 10 days after the contract award or notice to proceed. The identification matters because submission to that office is what starts the payment clock.
More Contract Admin Questions
When must a signal person be provided during a crane lift under subpart CC?
How may a signal person’s qualification be established under subpart CC?
What does subpart CC require to be carried on crane equipment itself?
A competent person’s excavation inspection finds evidence of a possible cave-in. What does s. 1926.651(k)(2) require?
What does a "permit application" comprise where a private provider has done the plan review?
A tenant asks the general contractor to begin demolition inside an existing space before the permit is issued. What does s. 553.79(1)(a) provide?
The enforcing agency determines that permitted work is not in conformity with the Florida Building Code. What may it do under s. 553.79(1)(a)?
A permit is denied because the plans are found not to comply. What must the local enforcing agency give the applicant?
What must a request for a certificate of occupancy include on a private provider job?
A rejected payment application is corrected and resubmitted to a city whose charter requires the commission to approve payments. When must the city pay or reject it?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass