The bid form requires separate unit prices for rock excavation and unsuitable soil removal. A civil quote combines them. What should the estimator do?

Correct Answer

D) Separate or clarify the unit prices before submitting the bid

Obtain separate supported prices for the two requested units or seek clarification through the allowed bidding channel. Duplicating a combined quote under both lines risks double counting and does not establish either unit rate. The subcontractor’s quote format does not amend the owner’s bid form.

Answer Options
A
Put the combined price under both lines and let the owner split it later
B
Delete one unit-price line because the subcontractor combined its quote
C
Resolve the difference only after final completion
D
Separate or clarify the unit prices before submitting the bid

Why This Is the Correct Answer

Obtain separate supported prices for the two requested units or seek clarification through the allowed bidding channel. Duplicating a combined quote under both lines risks double counting and does not establish either unit rate. The subcontractor’s quote format does not amend the owner’s bid form.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Contract Admin Questions

A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?

A court enforces a lien against the improvement alone rather than the land. What may it order?

A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?

Who can compel a local government to create a residential master building permit program?

Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?

A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?

What must accompany a bid for construction on a Florida public project under s. 489.131(2)?

A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?

For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?

Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.