Contract AdminPreconstructionmedium27% of exam part

The bid form requires separate unit prices for rock excavation and unsuitable soil removal. A civil quote combines them. What should the estimator do?

Correct Answer

D) Separate or clarify the unit prices before submitting the bid

The bid must respond to the requested pricing structure.

Answer Options
A
Put the combined price under both lines and let the owner split it later
B
Delete one unit-price line because the subcontractor combined its quote
C
Resolve the difference only after final completion
D
Separate or clarify the unit prices before submitting the bid

Why This Is the Correct Answer

The bid must respond to the requested pricing structure.

Why the Other Options Are Wrong

Option A: Put the combined price under both lines and let the owner split it later

Put the combined price under both lines and let the owner split it later skips the written authority, scope, price, notice, or release control needed for bid form compliance.

Option B: Delete one unit-price line because the subcontractor combined its quote

Delete one unit-price line because the subcontractor combined its quote skips the written authority, scope, price, notice, or release control needed for bid form compliance.

Option C: Resolve the difference only after final completion

Resolve the difference only after final completion skips the written authority, scope, price, notice, or release control needed for bid form compliance.

Memory Technique

Bid Form Compliance square for Site Includes: scope, authority, price, paper.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Bid preparation; unit prices and bid-form compliance; verify the quantity, approval point, notice rule, or field record before answering.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.