A contract says the contractor will obtain permits, but the owner asks to take over permit submittal. What should document that shift?
Correct Answer
B) Written responsibility change.
Changing permit responsibility alters a contract duty and should be documented in writing.
Why This Is the Correct Answer
Changing permit responsibility alters a contract duty and should be documented in writing.
Why the Other Options Are Wrong
Option A: Get the labor and material warranty terms in writing.
Choosing to get the labor and material warranty terms in writing does not address a change in who obtains permits.
Option C: Owner-approved substitution.
Owner-approved substitution does not address a change in who obtains permits.
Option D: Payment period.
Payment period does not address a change in who obtains permits.
Reference Hint
Study anchor (closed-book): memorize Project responsibility from CSLB 2026 Law Book; CSLB Home Improvement Contracts / Business and Professions Code Section 7159 written change order requirements; know the rule or calculation trigger without relying on exam-room lookup.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Law & Business Questions
A contractor pays workers through a payment app but does not issue itemized pay statements. What is missing?
Apply California’s standard overtime rules, with no alternative-workweek or other exception. A nonexempt worker at a regular rate of $36 per hour works 15 hours in one day. What is the day's gross pay, ignoring weekly overtime?
A supplier delivers special-order windows to the site, but the contract does not list when material payments are due. What should be checked?
A site checklist requires 31 separate SDS records, one for each listed product. It contains 27 valid records corresponding to 27 different listed products, with no duplicates or shared SDS entries. How many required records are missing?
In the bathroom addition file, cash is $28,000, receivables are $44,000, inventory is $16,000, and current liabilities are $60,000. What is the quick ratio?
A worker requests their own payroll records, but the company says only managers may see them. What should be reviewed?
Special-order cabinets are stored at the supplier, but the contract only pays for materials delivered to the job. What should be checked?
A contractor is unsure whether a publicly funded building upgrade is public work. What is the best first step?
A contractor's workers' compensation certificate lists the policy number but omits effective and expiration dates. What is the problem?
A jobsite stores flammable liquid next to ignition sources and exits. What is the best correction?
People Also Study
Related Study Resources
Previous Question
Apply California’s standard overtime rules, with no alternative-workweek or other exception. A nonexempt employee works 9 hours on the seventh consecutive day of work within the same workweek, at a regular rate of $30 per hour. What pay is due for that day?
Next Question
During ordinary construction cutting, a portable circular saw’s lower guard is tied open for speed. What is the appropriate response?