A supplier delivers special-order windows to the site, but the contract does not list when material payments are due. What should be checked?

Correct Answer

C) Payment schedule.

Material payment timing should be controlled by the written contract payment schedule and value delivered.

Answer Options
A
Assume the cheaper contract interpretation where a supplier delivers special-order windows to the site, but the contract does not list, and leave the written scope conflict unresolved.
B
Let the field crew sort out the paperwork later where a supplier delivers special-order windows to the site, but the contract does not list, instead of issuing the clarification before pricing the work.
C
Payment schedule.
D
A supplier quote that is not tied to the contract payment schedule.

Why This Is the Correct Answer

Material payment timing should be controlled by the written contract payment schedule and value delivered.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.