A jobsite stores flammable liquid next to ignition sources and exits. What is the best correction?
Correct Answer
B) Store and handle it away from ignition and exit hazards.
Flammable liquids need controlled storage and handling away from ignition and egress hazards.
Why This Is the Correct Answer
Flammable liquids need controlled storage and handling away from ignition and egress hazards.
Why the Other Options Are Wrong
Option A: Keep it there for convenience.
Keep it there for convenience. may relate to another site control, but it does not remove or guard the hazardous materials exposure being tested.
Option C: Pour it into unmarked drink bottles for faster access by the crew.
Pour it into unmarked drink bottles for faster access by the crew. may relate to another site control, but it does not remove or guard the hazardous materials exposure being tested.
Option D: Use it only when the inspector leaves.
Use it only when the inspector leaves. may relate to another site control, but it does not remove or guard the hazardous materials exposure being tested.
Memory Technique
If Correcting Jobsite can still reach the worker, the control is decoration.
Reference Hint
Study anchor (closed-book): memorize Hazardous materials from Cal/OSHA Title 8 Construction Safety Orders; CSLB Law and Business. / Title 8 flammable liquid storage and fire prevention requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?