A contractor's workers' compensation certificate lists the policy number but omits effective and expiration dates. What is the problem?
Correct Answer
B) CSLB certificate requirements include the effective date and expiration date.
CSLB states that the policy effective date and expiration date must be listed on the certificate.
Why This Is the Correct Answer
CSLB states that the policy effective date and expiration date must be listed on the certificate.
Why the Other Options Are Wrong
Option A: Dates are optional if the insurer name is shown.
Dates are optional if the insurer name is shown. misses the specific employer duty in workers' compensation filing; it does not resolve the pay, reimbursement, status, timing, or record issue.
Option C: Only the expiration date matters after the first year.
Only the expiration date matters after the first year. misses the specific employer duty in workers' compensation filing; it does not resolve the pay, reimbursement, status, timing, or record issue.
Option D: Dates can be replaced with the contractor's license issue date, even when the policy has a different current insurance period.
Dates can be replaced with the contractor's license issue date, even when the policy has a different current insurance period. misses the specific employer duty in workers' compensation filing; it does not resolve the pay, reimbursement, status, timing, or record issue.
Memory Technique
If the job needs states, the employer needs Reviewing Submitting proof.
Reference Hint
Study anchor (closed-book): memorize Workers' compensation filing from CSLB Workers' Compensation Requirements; CSLB Workers' Compensation. / CSLB workers' compensation insurance certificate requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?