A circular saw lower guard is tied open for speed. What should be done?
Correct Answer
D) Restore guard.
Tool guards should remain in place and operate as intended.
Why This Is the Correct Answer
Tool guards should remain in place and operate as intended.
Why the Other Options Are Wrong
Option A: Anchor point.
Anchor point. may relate to another site control, but it does not remove or guard the tool guarding exposure being tested.
Option B: Appropriate eye and face PPE.
Appropriate eye and face PPE. may relate to another site control, but it does not remove or guard the tool guarding exposure being tested.
Option C: As a serious injury.
As a serious injury. may relate to another site control, but it does not remove or guard the tool guarding exposure being tested.
Memory Technique
Tool Guarding lock for Correcting Carpentry: guards is the harm, remain is the guard.
Reference Hint
Study anchor (closed-book): memorize Tool guarding from Cal/OSHA Title 8; CSLB Law and Business Study Guide / Title 8 hand and power tool guarding requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?