An invoice charges full flooring material cost even though the contract has a flooring allowance. What should be corrected?
Correct Answer
C) Allowance math.
Allowance billing should reconcile the difference between the allowance and selected cost according to the contract.
Why This Is the Correct Answer
Allowance billing should reconcile the difference between the allowance and selected cost according to the contract.
Why the Other Options Are Wrong
Option A: Written change.
Written change does not address billing only the allowance difference.
Option B: Add schedule dates.
Choosing to add schedule dates does not address billing only the allowance difference.
Option D: Approval came late.
Approval came late does not address billing only the allowance difference.
Reference Hint
Study anchor (closed-book): memorize Allowance reconciliation from CSLB 2026 Law Book; CSLB Home Improvement Contracts / B&P Code Section 7159 home improvement contract requirements; know the rule or calculation trigger without relying on exam-room lookup.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Law & Business Questions
A contractor pays workers through a payment app but does not issue itemized pay statements. What is missing?
Apply California’s standard overtime rules, with no alternative-workweek or other exception. A nonexempt worker at a regular rate of $36 per hour works 15 hours in one day. What is the day's gross pay, ignoring weekly overtime?
A supplier delivers special-order windows to the site, but the contract does not list when material payments are due. What should be checked?
A site checklist requires 31 separate SDS records, one for each listed product. It contains 27 valid records corresponding to 27 different listed products, with no duplicates or shared SDS entries. How many required records are missing?
In the bathroom addition file, cash is $28,000, receivables are $44,000, inventory is $16,000, and current liabilities are $60,000. What is the quick ratio?
A worker requests their own payroll records, but the company says only managers may see them. What should be reviewed?
Special-order cabinets are stored at the supplier, but the contract only pays for materials delivered to the job. What should be checked?
A contractor is unsure whether a publicly funded building upgrade is public work. What is the best first step?
A contractor's workers' compensation certificate lists the policy number but omits effective and expiration dates. What is the problem?
A jobsite stores flammable liquid next to ignition sources and exits. What is the best correction?
People Also Study
Related Study Resources
Previous Question
A construction employer on a public-works project is covered by IWC Wage Order 16, with no exemption from section 6. Under section 6(C), what is the minimum retention period for the records required by that section, apart from any longer or additional applicable requirement?
Next Question
A worker requests a copy of their own payroll records, but the company says records are only for management. What should be reviewed?