Public works payroll records generally must be available for at least how long under Labor Code Section 1776?
Correct Answer
A) 3 years.
Labor Code Section 1776 includes a three-year payroll record availability period.
Why This Is the Correct Answer
Labor Code Section 1776 includes a three-year payroll record availability period.
Why the Other Options Are Wrong
Option B: One week.
One week. belongs to a different file or record trail; it does not prove the certified payroll records event.
Option C: One month.
One month. belongs to a different file or record trail; it does not prove the certified payroll records event.
Option D: Ten days.
Ten days. belongs to a different file or record trail; it does not prove the certified payroll records event.
Memory Technique
File Setting Public where the next reviewer would look first.
Reference Hint
Study anchor (closed-book): memorize Certified payroll records from California Labor Code Sections 1771.4 and 1776; DIR certified payroll. / California Labor Code Section 1776 payroll records; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?