Cost ApproachMEDIUM13.6% of exam

The improvement budget has direct costs $365,000, indirect costs $48,000, and an additional supported entrepreneurial incentive $67,000 not already included in either. Land is separate. What full improvement cost new results?

Correct Answer

D) $480,000

365000+48000+67000 = 480000. Common errors: leaving out the entrepreneurial incentive gives $413,000; leaving out the indirect costs gives $432,000; reporting only the direct costs gives $365,000.

Answer Options
A
$365,000
B
$413,000
C
$432,000
D
$480,000

Why This Is the Correct Answer

Option D is correct because full economic cost includes all direct and indirect costs plus market-supported entrepreneurial profit or incentive: $365,000 + $48,000 + $67,000 = $480,000.

Why the Other Options Are Wrong

Option A: $365,000

Option A, $365,000, reports only the direct costs. It omits the $48,000 indirect costs and the $67,000 entrepreneurial incentive; the full total is $480,000.

Option B: $413,000

Option B, $413,000, adds direct and indirect costs ($365,000 + $48,000) but leaves out the $67,000 entrepreneurial incentive. Including it gives $480,000.

Option C: $432,000

Option C, $432,000, adds direct costs and incentive ($365,000 + $67,000) but leaves out the $48,000 indirect costs. Including them gives $480,000.

Direct, indirect, incentive

Full cost new has three parts: direct, indirect and incentive. Land stays outside.

How to use: Use this three-part list to check that a cost new figure is complete.

Exam Tip

Watch for wording that says the incentive is or is not already included. If it is separate, add it; if it is already in the budget, do not add it twice.

Common Mistakes to Avoid

  • -Omitting entrepreneurial incentive from cost new
  • -Leaving out indirect costs
  • -Including land value in improvement cost new

Concept Deep Dive

Analysis

This question tests what is included in full improvement cost new. Full economic cost combines direct costs, indirect costs and entrepreneurial incentive. Since the incentive is stated as not already included, all three amounts are added.

Background Knowledge

The cost approach should reflect full economic cost: direct costs, indirect costs and a market-supported entrepreneurial profit or incentive. The appraiser must account for all direct and indirect costs of constructing the improvements. Land is valued separately and is not part of improvement cost.

Real-World Application

An appraiser valuing a newly built home adds the builder's labor and materials, the indirect costs and a market-supported developer incentive. The site value from land sales is added later, separately from the improvement cost.

entrepreneurial incentivedirect costsindirect costsfull economic costcost new
Was this explanation helpful?

More Cost Approach Questions

Why can equivalent-utility replacement cost be useful for an obsolete improvement?

An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?

Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?

What best supports a claimed loss from a bathroom-layout deficiency?

Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?

Which scenario most strongly supports giving the cost approach substantial weight?

A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?

A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?

A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?

An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?

People Also Study

Practice More Appraiser Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Appraiser exam.

Start Practicing