EstatePass
Cost ApproachMEDIUM13.6% of exam

The only soft costs in a construction budget are architecture/engineering $27,000, construction financing interest $19,000, permits/impact fees $8,500 and construction-period property taxes $6,500. What is the total soft cost?

Correct Answer

D) $61,000

27000+19000+8500+6500 = 61000. Common errors: leaving out the construction financing interest gives $42,000; leaving out the construction-period property taxes gives $54,500; leaving out permits/fees and construction-period taxes gives $46,000.

Answer Options
A
$42,000
B
$46,000
C
$54,500
D
$61,000

Why This Is the Correct Answer

Option D is correct because total soft cost is the sum of the four listed items: $27,000 + $19,000 + $8,500 + $6,500 = $61,000.

Why the Other Options Are Wrong

Option A: $42,000

Option A, $42,000, leaves out the $19,000 construction financing interest ($27,000 + $8,500 + $6,500). Financing interest during construction is a soft cost, so the total is $61,000.

Option B: $46,000

Option B, $46,000, includes only architecture/engineering and financing interest ($27,000 + $19,000). It omits the $8,500 permits/fees and $6,500 taxes; the full total is $61,000.

Option C: $54,500

Option C, $54,500, leaves out the $6,500 construction-period property taxes ($27,000 + $19,000 + $8,500). Adding them gives $61,000.

Hard you build, soft you pay

Hard costs go into the physical structure; soft costs are the fees, interest, permits and taxes paid to get it built.

How to use: Use this to sort each budget line into hard or soft before adding.

Exam Tip

When a question lists several items for a subtotal, count them and make sure each one is in your sum. Distractors often drop one item.

Common Mistakes to Avoid

  • -Leaving construction loan interest out of soft costs
  • -Omitting property taxes paid during construction
  • -Treating permits and fees as hard costs

Concept Deep Dive

Analysis

This question tests identifying and summing indirect (soft) costs. All four listed items are stated to be soft costs for this subtotal. Add architecture and engineering, financing interest, permits and fees, and construction-period taxes.

Background Knowledge

Full economic cost includes direct (hard) costs, indirect (soft) costs and market-supported entrepreneurial profit. Hard costs are the on- and off-site construction costs such as labor and materials. Soft costs include items like professional fees, construction financing, permits and fees, and taxes during construction.

Real-World Application

Reviewing a builder's budget for a new home, an appraiser separates the lumber and labor from the design fees, loan interest, permit charges and taxes during construction. The appraiser confirms the soft costs are included so the cost estimate reflects full economic cost.

soft costsindirect costshard costsconstruction financingfull economic cost
Was this explanation helpful?

More Cost Approach Questions

Why can equivalent-utility replacement cost be useful for an obsolete improvement?

An appraiser estimates the current replacement cost new of the improvements at $890,000, accrued depreciation from all causes at $170,000, and land value at $325,000. All necessary cost components and depreciation are included in those amounts. What is the indicated property value?

Improvement cost new is $595,000. Separately supported improvement depreciation deductions of $48,000, $27,000 are expressly nonoverlapping and not already excluded from cost new. Add supported site value of $155,000, already reflecting any site losses. What total indicated value results?

What best supports a claimed loss from a bathroom-layout deficiency?

Improvement cost new is $1,850,000. Separately supported improvement depreciation deductions of $310,000, $620,000 are expressly nonoverlapping and not already excluded from cost new. No site is included. What depreciated improvement amount results?

Which scenario most strongly supports giving the cost approach substantial weight?

A cost total $650,000 explicitly includes $40,000 of non-realty FF&E outside the appraised real-property interest. Exclude it. Supported realty-only total depreciation is $55,000. Add site $200,000, with no overlap. What real-property cost indication results?

A 2,200-sf dwelling costs $200 per square foot, and a separate 400-sf garage costs $75 per square foot. These costs are complete and do not overlap. Both have an effective age of 15 years and a total life of 50 years, with straight-line depreciation and no salvage value. No site value or other loss is involved. What is the combined depreciated cost of the dwelling and garage?

A new feature in the improvements has a current cost of $45,000 and a market contribution of $18,000. The entire difference is due to superadequacy, with no physical or external loss and no overlap. What is the loss from the superadequacy?

An external influence causes an annual net income loss of $9,600. The capitalization rate for the loss is 8%, and no other economic factors change. What is the indicated loss in value of the whole property, before allocation between site and improvements?

People Also Study

Practice More Appraiser Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Appraiser exam.

Start Practicing