A buyer in Vermont is under contract to purchase a 12-lot subdivision from a developer. The buyer's agent mentions that the project may require an Act 250 permit. Under 10 V.S.A. Chapter 151, which of the following best explains why Act 250 likely applies to this transaction?

Correct Answer

B) Act 250 applies because the subdivision involves 10 or more lots, which meets the statutory threshold requiring a land use permit

Under 10 V.S.A. Chapter 151, Vermont's Act 250 requires a land use permit for subdivisions of 10 or more lots. Because this project involves a 12-lot subdivision, it meets the threshold and Act 250 review is required. The project must satisfy all 10 statutory criteria covering environmental and community impacts before the permit is granted.

Answer Options
A
Act 250 applies because the total purchase price exceeds $500,000, triggering mandatory state environmental review
B
Act 250 applies because the subdivision involves 10 or more lots, which meets the statutory threshold requiring a land use permit
C
Act 250 applies because the buyer is a corporation rather than an individual purchaser under Vermont law
D
Act 250 applies because any subdivision in Vermont with more than five lots requires a state environmental permit

Why This Is the Correct Answer

Sign up free to unlock full analysis

Why the Other Options Are Wrong

Sign up free to unlock full analysis

Deep Analysis of This Contracts Question

Sign up free to unlock full analysis

Background Knowledge for Contracts

Sign up free to unlock full analysis
Sign up free to unlock full analysis

Real World Application in Contracts

Sign up free to unlock full analysis

Common Mistakes to Avoid on Contracts Questions

Sign up free to unlock full analysis

Related Topics & Key Terms

Key Terms:

act_250subdivisionland_use_permitdevelopment_thresholdsvermont_specific

Related Concepts

Equitable title is the buyer's interest in a property after a purchase contract is signed but before closing, giving the buyer the right to acquire legal title in the future. The seller retains legal title until the deed is delivered at closing.

A financing contingency makes the purchase contract conditional upon the buyer obtaining mortgage approval within a specified time period. If the buyer cannot secure financing, they can cancel the contract and receive their earnest money back.

An inspection contingency gives the buyer the right to have the property professionally inspected within a specified time frame and to negotiate repairs or cancel the contract based on the findings.

Was this explanation helpful?

More Contracts Questions

People Also Study

Related Articles

Contracts Questions

Practice More Questions

Access 2,000+ practice questions and pass your real estate exam.

Start Practicing