EIFS foam board is installed down to finished soil at a landscaped wall base. The detail requires clearance above grade. What is the proper field response?
Correct Answer
C) Trim and terminate EIFS at the required clearance with proper base detail
EIFS should be terminated at the required clearance above grade with the proper base detail to limit moisture, insects, and impact damage. Other choices bury or conceal a moisture-sensitive base condition.
Why This Is the Correct Answer
EIFS should be terminated at the required clearance above grade with the proper base detail to limit moisture, insects, and impact damage. Other choices bury or conceal a moisture-sensitive base condition.
Why the Other Options Are Wrong
Option A: Accept it because soil protects the base
In thermal and moisture protection, Accept it because soil protects the base is the wrong selection for EIFS base termination: it points to Accept it because soil protects the base, but.
Option B: Bury the mesh coat for impact resistance, leaving eIFS base termination unverified
The trap in B is Bury the mesh coat for impact resistance. That selection is wrong because it answers the EIFS base termination prompt with the wrong practical move.
Option D: The roofing crew should paint the below-grade foam black
Choice D (Paint the below-grade foam black) is rejected because the option shifts to a different trade task; the tested EIFS base termination function or field correction is Trim and terminate EIFS at the required clearance with proper base detail.
Memory Technique
Use the phrase "problem, control, result" for EIFS base termination; the result side is Trim and terminate EIFS at the required clearance with proper base detail.
Reference Hint
Open ANSI/EIMA 99-A-2017, Exterior Insulation and Finish Systems; use the index entry or section for "ANSI/EIMA 99-A-2017 EIFS base termination and clearance" to confirm that EIFS should be terminated at the required clearance above grade with the proper base detail to limit moisture, insects, and impact damage.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
