Why is dewatering planned before excavation proceeds?
Correct Answer
A) To control groundwater so excavation stability, access, and discharge quality can be managed
Dewatering planning addresses groundwater control, excavation safety, access, and permitted discharge.
Why This Is the Correct Answer
Dewatering planning addresses groundwater control, excavation safety, access, and permitted discharge.
Why the Other Options Are Wrong
Option B: Use dewatering planning to calculate retainage
Choice B gives To calculate retainage. Its specific error: it shifts the question into contract administration money flow.
Option C: Use dewatering planning to approve drywall
Choice C (To approve drywall) is rejected because it leaves out the controlling Dewatering planning result: To control groundwater so excavation stability, access, and discharge quality can be managed.
Option D: Use dewatering planning to replace utility locating and treat the neighboring item as controlling dewatering planning
In site construction, To replace utility locating is the wrong selection for Dewatering planning: the option tries to substitute, waive, or delete the Dewatering planning control; the item instead requires To control groundwater so excavation stability, access, and discharge quality can be managed.
Memory Technique
Picture dewatering planning doing the job; the answer names that job as To control groundwater so excavation stability, access, and discharge quality can be managed.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use by topic index - dewatering to confirm that Dewatering planning addresses groundwater control, excavation safety, access, and permitted discharge.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
