What is the purpose of a stabilized construction entrance?
Correct Answer
A) Reduce sediment tracking from the site onto public roads
A stabilized construction entrance reduces sediment trackout from construction vehicles leaving the site.
Why This Is the Correct Answer
A stabilized construction entrance reduces sediment trackout from construction vehicles leaving the site.
Why the Other Options Are Wrong
Option B: The site crew should increase trench depth
In site construction, Increase trench depth is the wrong selection for Stabilized entrance purpose: it answers the Stabilized entrance purpose prompt with the wrong practical move.
Option C: The site crew should replace utility locates
The trap in C is Replace utility locates. That selection is wrong because it removes the controlling Stabilized entrance purpose requirement instead of meeting it.
Option D: Serve as a final survey benchmark
Choice D gives Serve as a final survey benchmark. Its specific error: the choice would not get the project to Reduce sediment tracking from the site onto public roads, which is the Stabilized entrance purpose result verified by the source.
Memory Technique
Link stabilized entrance purpose to its book condition; a different condition means a different answer than Reduce sediment tracking from the site onto public roads.
Reference Hint
Open Developing Your Stormwater Pollution Prevention Plan, EPA 833-R-06-004, 2007; use the index entry or section for "EPA 833-R-06-004 - erosion and sediment controls" to confirm that A stabilized construction entrance reduces sediment trackout from construction vehicles leaving the site.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?