A trench shield's tabulated data covers depths up to 12 ft, but the planned pipe run reaches 15 ft in the same soil. What should the superintendent require?
Correct Answer
D) Use a protective system within its tabulated data or obtain a registered professional engineer's design
Protective systems must be used within their tabulated data or be designed by a registered professional engineer for the actual conditions. Other choices rely on an unapproved use or unsafe equipment support.
Why This Is the Correct Answer
Protective systems must be used within their tabulated data or be designed by a registered professional engineer for the actual conditions. Other choices rely on an unapproved use or unsafe equipment support.
Why the Other Options Are Wrong
Option A: Use the box because the difference is only 3 ft
Choice A (Use the box because the difference is only 3 ft) is rejected because Use the box because the difference is only 3 ft uses the wrong excavation protective-system trigger or exception.
Option B: Stack spoil against the box to stiffen it
In site construction, Stack spoil against the box to stiffen it is the wrong selection for Trench shield limitations: the choice would not get the project to Use a protective system within its tabulated data or obtain a registered professional engineer's design, which is the Trench shield limitations result verified by the source.
Option C: Enter only while the excavator holds the shield and leave trench shield limitations unchecked
The trap in C is Enter only while the excavator holds the shield. That selection is wrong because it leaves the work at an informal or incomplete stage, while Trench shield limitations requires Use a protective system within its tabulated data or obtain a registered professional engineer's.; Protective systems must match tabulated data or a registered professional engineer design.
Memory Technique
Use the phrase "problem, control, result" for trench shield limitations; the result side is Use a protective system within its tabulated data or obtain a registered professional engineer's design.
Reference Hint
Open 29 CFR Part 1926, Subpart P - Excavations; use 29 CFR 1926.652(c) to confirm that Protective systems must be used within their tabulated data or be designed by a registered professional engineer for the actual conditions.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
