A pad needs 950 compacted cubic yards of structural fill. If the borrow material yields 0.85 compacted cubic yard for each bank cubic yard, what bank volume is required?
Correct Answer
D) 1,118 bcy
Required bank volume is 950/0.85 = 1,117.6 bcy, rounded to 1,118 bcy. Other choices multiply instead of divide, use a 0.90 yield, or add an arbitrary swell factor.
Why This Is the Correct Answer
Required bank volume is 950/0.85 = 1,117.6 bcy, rounded to 1,118 bcy. Other choices multiply instead of divide, use a 0.90 yield, or add an arbitrary swell factor.
Why the Other Options Are Wrong
Option A: 808 bcy
compacted fill yield, choice a: 808 bcy uses the wrong numerator, denominator, or percent conversion.
Option B: 1,073 bcy
compacted fill yield, choice b: 1,073 bcy is wrong because 1,073 bcy uses the wrong numerator, denominator, or percent conversion.
Option C: 1,235 bcy
compacted fill yield, choice d: 1,235 bcy uses the wrong numerator, denominator, or percent conversion.
Memory Technique
Store compacted fill yield with its last math move; nearby answers are usually unfinished versions of 1,118 bcy.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Earthwork shrink and yield calculation" to confirm that Required bank volume is 950/0.85 = 1,117.6 bcy, rounded to 1,118 bcy.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass