Who commonly bears quantity variation risk in a unit-price item?
Correct Answer
C) The final price varies with measured quantities under the contract.
Unit-price payment adjusts to measured quantities according to contract terms.
Why This Is the Correct Answer
Unit-price payment adjusts to measured quantities according to contract terms.
Why the Other Options Are Wrong
Option A: The quantity can never change
Choice A (The quantity can never change.) is rejected because the choice would not get the project to The final price varies with measured quantities under the contract.
Option B: The bidder is paid the bid quantity only regardless of measurement
In procurement and contracting, The bidder is paid the bid quantity only regardless of measurement. is the wrong selection for Unit-price quantity risk: the action skips the timing, documentation, or field-control step needed for Unit-price quantity risk.
Option D: The architect pays all overruns personally
Choice D gives The architect pays all overruns personally. Its specific error: the option answers a paperwork, payment, or bonding issue.
Memory Technique
Use unit-price quantity risk as the label and The final price varies with measured quantities under the contract. as the definition to recall under pressure.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Unit-price payment" to confirm that Unit-price payment adjusts to measured quantities according to contract terms.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
