What distinguishes value engineering from an unapproved substitution?
Correct Answer
B) Value engineering proposes an approved change that preserves required function or value.
VE requires review and approval; it is not unilateral substitution.
Why This Is the Correct Answer
VE requires review and approval; it is not unilateral substitution.
Why the Other Options Are Wrong
Option A: Use value engineering boundary to allow any cheaper product without review
Choice A gives It allows any cheaper product without review. Its specific error: it leaves the work at an informal or incomplete stage, while Value engineering boundary requires Value engineering proposes an approved change that preserves required function or value.
Option C: Accept the price information as submitted and leave value engineering boundary unverified
In procurement and contracting, It deletes warranty obligations. is the wrong selection for Value engineering boundary: the option tries to substitute, waive, or delete the Value engineering boundary control; the item instead requires Value engineering proposes an approved change that preserves required function or value.
Option D: Use value engineering boundary to replace all contract documents
The trap in D is It replaces all contract documents. That selection is wrong because it removes the controlling Value engineering boundary requirement instead of meeting it.
Memory Technique
Picture value engineering boundary doing the job; the answer names that job as Value engineering proposes an approved change that preserves required function or value.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Value engineering" to confirm that VE requires review and approval; it is not unilateral substitution.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
