What control is especially important for time-and-material work?
Correct Answer
A) Signed daily tickets showing labor, equipment, material, and authorization.
T&M work needs contemporaneous tickets because payment is based on actual time and material.
Why This Is the Correct Answer
T&M work needs contemporaneous tickets because payment is based on actual time and material.
Why the Other Options Are Wrong
Option B: Treat the condition as requiring no records until final completion
Choice B gives No records until final completion. Its specific error: the option does not produce the required Time-and-material control outcome, Signed daily tickets showing labor, equipment, material, and authorization.
Option C: Base the time-and-material control response on a lump-sum bid form only
Choice C (Only a lump-sum bid form.) is rejected because the option delays or omits the controlling step.
Option D: Base the time-and-material control response on an insurance certificate
In procurement and contracting, Only an insurance certificate. is the wrong selection for Time-and-material control: the action skips the timing, documentation, or field-control step needed for Time-and-material control.
Memory Technique
Keep time-and-material control as a cause-to-effect card with Signed daily tickets showing labor, equipment, material, and authorization. on the back.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Time and material work" to confirm that T&M work needs contemporaneous tickets because payment is based on actual time and material.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?