EstatePass
NASCLAProcurement and Contracting Requirementsmedium

A subcontract omits a prime-contract safety requirement applicable to the subcontractor's work. What should the contractor correct?

Correct Answer

C) Flow down the applicable prime-contract requirement into the subcontract documents.

Applicable prime-contract obligations must be flowed down to lower-tier parties.

Answer Options
A
Assume the subcontract flow-down requirement no longer applies
B
The contractor should wait for final payment
C
Flow down the applicable prime-contract requirement into the subcontract documents.
D
The contractor should replace safety requirements with a bid tab

Why This Is the Correct Answer

Applicable prime-contract obligations must be flowed down to lower-tier parties.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.