A supplier misses a committed delivery date for long-lead gear. What should procurement do?
Correct Answer
B) Check contract remedies, expedite alternatives, document impacts, and protect notice rights.
Supplier default requires contractual, recovery, and notice controls.
Why This Is the Correct Answer
Supplier default requires contractual, recovery, and notice controls.
Why the Other Options Are Wrong
Option A: The contractor should ignore the delay until substantial completion
Choice A gives Ignore the delay until substantial completion. Its specific error: it leaves the work at an informal or incomplete stage, while Supplier default recovery requires Check contract remedies, expedite alternatives, document impacts, and protect notice rights.
Option C: Release the supplier from all terms verbally, leaving supplier default recovery unverified
In procurement and contracting, Release the supplier from all terms verbally. is the wrong selection for Supplier default recovery: the action skips the timing, documentation, or field-control step needed for Supplier default recovery.
Option D: The contractor should delete the procurement log
The trap in D is Delete the procurement log. That selection is wrong because it removes the controlling Supplier default recovery requirement instead of meeting it.
Memory Technique
Remember supplier default recovery by its jobsite consequence: the correct move points to Check contract remedies, expedite alternatives, document impacts, and protect notice rights.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Supplier default" to confirm that Supplier default requires contractual, recovery, and notice controls.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
