NASCLAContractsmedium27% of exam part

A warranted door hardware failure occurs after turnover. What should the owner issue or contractor document?

Correct Answer

A) A warranty service request identifying the defect, date, location, and required correction.

Warranty correction should be documented with enough information to evaluate and perform the obligation.

Answer Options
A
A warranty service request identifying the defect, date, location, and required correction.
B
Classify the condition as a new bid bond as a bonding paperwork issue that controls warranty correction notice
C
Accept the price information as submitted and leave warranty correction notice unverified
D
Classify the condition as a noncollusion affidavit, leaving warranty correction notice unverified

Why This Is the Correct Answer

Warranty correction should be documented with enough information to evaluate and perform the obligation.

Why the Other Options Are Wrong

Option B: Classify the condition as a new bid bond as a bonding paperwork issue that controls warranty correction notice

Choice B gives A new bid bond. Its specific error: it names a financial document or payment mechanism, not the Warranty correction notice action/result stated by A warranty service request identifying the defect, date, location, and required correction.

Option C: Accept the price information as submitted and leave warranty correction notice unverified

Choice C (A deleted addendum) is rejected because the option tries to substitute, waive, or delete the Warranty correction notice control; the item instead requires A warranty service request identifying the defect, date, location, and required correction.

Option D: Classify the condition as a noncollusion affidavit, leaving warranty correction notice unverified

In procurement and contracting, A noncollusion affidavit is the wrong selection for Warranty correction notice: the option does not produce the required Warranty correction notice outcome, A warranty service request identifying the defect, date, location, and required correction.

Memory Technique

Use the phrase "problem, control, result" for warranty correction notice; the result side is A warranty service request identifying the defect, date, location, and required correction.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Warranty service requests" to confirm that Warranty correction should be documented with enough information to evaluate and perform the obligation.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.