A contractor requests final payment but record drawings and warranties are missing. What is the issue?

Correct Answer

D) Closeout deliverables required before final payment are incomplete.

Final payment is commonly conditioned on required closeout documents.

Answer Options
A
Apply bid security is too low to the final payment closeout condition
B
The prebid meeting was too long
C
The OSHA poster is missing from the bid, leaving final payment closeout unverified
D
Closeout deliverables required before final payment are incomplete.

Why This Is the Correct Answer

Final payment is commonly conditioned on required closeout documents.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.