A pay application includes materials stored in a warehouse. What should be verified before approval?
Correct Answer
B) Contract allowance, invoices, title/allocation, storage, protection, and insurance requirements.
Stored-material payment requires backup showing the material is eligible and protected.
Why This Is the Correct Answer
Stored-material payment requires backup showing the material is eligible and protected.
Why the Other Options Are Wrong
Option A: Base the pay application stored backup response on the warehouse paint color
Choice A (Only the warehouse paint color.) is rejected because it tries to bypass the Pay application stored backup checkpoint.
Option C: Base the pay application stored backup response on the bid spread
The trap in C is Only the bid spread. That selection is wrong because the option delays or omits the controlling step.
Option D: Base the pay application stored backup response on the final warranty letter
Choice D gives Only the final warranty letter. Its specific error: the action skips the timing, documentation, or field-control step needed for Pay application stored backup.
Memory Technique
Picture a tab on the jobsite; pay application stored backup is solved by the action that leads to Contract allowance, invoices, title/allocation, storage, protection, and insurance requirements.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Stored-material pay application" to confirm that Stored-material payment requires backup showing the material is eligible and protected.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass