A contractor front-loads mobilization and early activities in the schedule of values. What should the owner/CM review?
Correct Answer
A) Whether values reasonably allocate contract price to actual work and avoid overpayment risk.
Front-loaded values can create overpayment risk before work is in place.
Why This Is the Correct Answer
Front-loaded values can create overpayment risk before work is in place.
Why the Other Options Are Wrong
Option B: Whether it increases the bid bond as a bonding paperwork issue that controls schedule of values imbalance
Choice B (Whether it increases the bid bond.) is rejected because it names a financial document or payment mechanism, not the Schedule of values imbalance action/result stated by Whether values reasonably allocate contract price to actual work and avoid overpayment risk.
Option C: Apply whether it deletes the specs to the schedule of values imbalance condition
In procurement and contracting, Whether it deletes the specs. is the wrong selection for Schedule of values imbalance: the option tries to substitute, waive, or delete the Schedule of values imbalance control; the item instead requires Whether values reasonably allocate contract price to actual work and avoid overpayment risk.
Option D: Limit schedule of values imbalance to whether it waives insurance
The trap in D is Whether it waives insurance. That selection is wrong because it removes the controlling Schedule of values imbalance requirement instead of meeting it.
Memory Technique
Tag the scene with schedule of values imbalance: wrong actor or wrong timing means the fix is not Whether values reasonably allocate contract price to actual work and avoid overpayment risk.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Schedule of values review" to confirm that Front-loaded values can create overpayment risk before work is in place.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass