A contractor front-loads mobilization and early activities in the schedule of values. What should the owner/CM review?

Correct Answer

A) Whether values reasonably allocate contract price to actual work and avoid overpayment risk.

Front-loaded values can create overpayment risk before work is in place.

Answer Options
A
Whether values reasonably allocate contract price to actual work and avoid overpayment risk.
B
Whether it increases the bid bond as a bonding paperwork issue that controls schedule of values imbalance
C
Apply whether it deletes the specs to the schedule of values imbalance condition
D
Limit schedule of values imbalance to whether it waives insurance

Why This Is the Correct Answer

Front-loaded values can create overpayment risk before work is in place.

Why the Other Options Are Wrong

Option B: Whether it increases the bid bond as a bonding paperwork issue that controls schedule of values imbalance

Choice B (Whether it increases the bid bond.) is rejected because it names a financial document or payment mechanism, not the Schedule of values imbalance action/result stated by Whether values reasonably allocate contract price to actual work and avoid overpayment risk.

Option C: Apply whether it deletes the specs to the schedule of values imbalance condition

In procurement and contracting, Whether it deletes the specs. is the wrong selection for Schedule of values imbalance: the option tries to substitute, waive, or delete the Schedule of values imbalance control; the item instead requires Whether values reasonably allocate contract price to actual work and avoid overpayment risk.

Option D: Limit schedule of values imbalance to whether it waives insurance

The trap in D is Whether it waives insurance. That selection is wrong because it removes the controlling Schedule of values imbalance requirement instead of meeting it.

Memory Technique

Tag the scene with schedule of values imbalance: wrong actor or wrong timing means the fix is not Whether values reasonably allocate contract price to actual work and avoid overpayment risk.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Schedule of values review" to confirm that Front-loaded values can create overpayment risk before work is in place.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.