NASCLAProcurement and Contracting Requirementsmedium

A contractor front-loads mobilization and early activities in the schedule of values. What should the owner/CM review?

Correct Answer

A) Whether values reasonably allocate contract price to actual work and avoid overpayment risk.

Front-loaded values can create overpayment risk before work is in place.

Answer Options
A
Whether values reasonably allocate contract price to actual work and avoid overpayment risk.
B
Whether it increases the bid bond as a bonding paperwork issue that controls schedule of values imbalance
C
Apply whether it deletes the specs to the schedule of values imbalance condition
D
Limit schedule of values imbalance to whether it waives insurance

Why This Is the Correct Answer

Front-loaded values can create overpayment risk before work is in place.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.