When are unit prices especially useful?
Correct Answer
A) When final quantities may vary and payment can be based on measured units.
Unit prices support payment adjustment when measured quantities differ.
Why This Is the Correct Answer
Unit prices support payment adjustment when measured quantities differ.
Why the Other Options Are Wrong
Option B: When no quantities will be measured
In procurement and contracting, When no quantities will be measured. is the wrong selection for Unit price contract use: it leaves out the controlling Unit price contract use result: When final quantities may vary and payment can be based on measured units.
Option C: When all work is paid only by salary
The trap in C is When all work is paid only by salary. That selection is wrong because it tries to bypass the Unit price contract use checkpoint.
Option D: When the owner wants no price basis
Choice D gives When the owner wants no price basis. Its specific error: the option does not produce the required Unit price contract use outcome, When final quantities may vary and payment can be based on measured units.
Memory Technique
Use a closeout folder memory cue for unit price contract use: the stem's condition unlocks When final quantities may vary and payment can be based on measured units.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Unit prices" to confirm that Unit prices support payment adjustment when measured quantities differ.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?