What is an allowance in the contract sum?
Correct Answer
D) A stated amount included for work or items not fully defined at bid time.
Allowances carry a stated amount until final selection or scope is reconciled.
Why This Is the Correct Answer
Allowances carry a stated amount until final selection or scope is reconciled.
Why the Other Options Are Wrong
Option A: Base the allowance definition response on a contractor's hidden contingency
Choice A gives A contractor's hidden contingency only. Its specific error: the option delays or omits the controlling step.
Option B: Classify the condition as a deleted scope item
Choice B (A deleted scope item.) is rejected because the option tries to substitute, waive, or delete the Allowance definition control; the item instead requires A stated amount included for work or items not fully defined at bid time.
Option C: Classify the condition as a warranty certificate
In procurement and contracting, A warranty certificate. is the wrong selection for Allowance definition: the option does not produce the required Allowance definition outcome, A stated amount included for work or items not fully defined at bid time.
Memory Technique
Link allowance definition to its book condition; a different condition means a different answer than A stated amount included for work or items not fully defined at bid time.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Allowances" to confirm that Allowances carry a stated amount until final selection or scope is reconciled.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
Next Question
A contract allows 10 percent overhead and then 5 percent profit on a $18,000 direct-cost change. If profit is applied after overhead, what total proposal amount results?