What is the usual purpose of a notice to proceed?
Correct Answer
B) Authorize the contractor to start contract time or begin the work as stated.
The notice to proceed commonly triggers contract time or work authorization.
Why This Is the Correct Answer
The notice to proceed commonly triggers contract time or work authorization.
Why the Other Options Are Wrong
Option A: The contractor should approve final completion
In procurement and contracting, Approve final completion. is the wrong selection for Notice to proceed: the option does not produce the required Notice to proceed outcome, Authorize the contractor to start contract time or begin the work as stated.
Option C: Release all retainage
Choice C gives Release all retainage. Its specific error: it shifts the question into contract administration money flow.
Option D: Cancel required insurance
Choice D (Cancel required insurance.) is rejected because it leaves out the controlling Notice to proceed result: Authorize the contractor to start contract time or begin the work as stated.
Memory Technique
File notice to proceed under a dimension string: condition first, number or duty second, answer Authorize the contractor to start contract time or begin the work as stated.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Notice to proceed" to confirm that The notice to proceed commonly triggers contract time or work authorization.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?