Why should an unconditional lien waiver not be given before payment clears?
Correct Answer
A) It may release lien rights even if payment is not actually received.
Unconditional waivers can release rights without a payment condition.
Why This Is the Correct Answer
Unconditional waivers can release rights without a payment condition.
Why the Other Options Are Wrong
Option B: Use unconditional lien waiver risk to increas the bid bond
In procurement and contracting, It increases the bid bond. is the wrong selection for Unconditional lien waiver risk: it shifts the question into contract administration money flow.
Option C: Use unconditional lien waiver risk to create a new allowance
The trap in C is It creates a new allowance. That selection is wrong because the choice would not get the project to It may release lien rights even if payment is not actually received. which is the Unconditional lien waiver risk result verified by the source.
Option D: Use unconditional lien waiver risk to change the specification section
Choice D gives It changes the specification section. Its specific error: the option does not produce the required Unconditional lien waiver risk outcome, It may release lien rights even if payment is not actually received.
Memory Technique
Treat unconditional lien waiver risk like a labeled shelf; only the matching condition belongs with It may release lien rights even if payment is not actually received.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Lien waivers" to confirm that Unconditional waivers can release rights without a payment condition.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?