Before backfill begins, why does prompt notice matter for a differing site condition?
Correct Answer
D) It preserves review before the condition is disturbed
It preserves review before the condition is disturbed is the correct meaning of divergent site condition in this construction context for concept item 535. Other choices: the distractors describe unrelated administration, payment, or closeout ideas.
Why This Is the Correct Answer
It preserves review before the condition is disturbed is the correct meaning of divergent site condition in this construction context for concept item 535.
Why the Other Options Are Wrong
Option A: It approves every claim; without required owner or contract approval
The trap in A is It approves every claim; without required owner or contract approval. That selection is wrong because it leaves the work at an informal or incomplete stage, while Divergent site condition requires.
Option B: It replaces a bid bond
Choice B gives It replaces a bid bond. Its specific error: the option tries to substitute, waive, or delete the Divergent site condition control; the item instead requires.
Option C: Use the payment application file as the backup record for divergent site condition
Choice C (It closes the punch list) is rejected because it answers the Divergent site condition prompt with the wrong practical move.
Memory Technique
Picture divergent site condition doing the job; the answer names that job as It preserves review before the condition is disturbed.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Differing site condition" to confirm that It preserves review before the condition is disturbed is the correct meaning of divergent site condition in this construction context for concept item 535.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass