A bidder wants to protest an award decision. What should be checked first?
Correct Answer
D) The protest procedure and deadline in the procurement documents or law.
Bid protests are time-sensitive and procedure-driven.
Why This Is the Correct Answer
Bid protests are time-sensitive and procedure-driven.
Why the Other Options Are Wrong
Option A: Close contract execution first and resolve the bid protest clock record later
In procurement and contracting, The warranty manual is the wrong selection for Bid protest clock: the choice would not get the project to The protest procedure and deadline in the procurement documents or law.
Option B: The bidder should check the subcontractor's safety inspection schedule after award
The trap in B is The scaffold inspection tag. That selection is wrong because the option does not produce the required Bid protest clock outcome, The protest procedure and deadline in the procurement documents or law.
Option C: Use a later change request to handle bid protest clock after award
Choice C gives The punch-list paint color. Its specific error: it describes work from another assembly, while the Bid protest clock item is asking for The protest procedure and deadline in the procurement documents or law.
Memory Technique
Use the phrase "problem, control, result" for bid protest clock; the result side is The protest procedure and deadline in the procurement documents or law.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bid protest procedure" to confirm that Bid protests are time-sensitive and procedure-driven.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
