EstatePass
NASCLAContractsmedium27% of exam part

Unexpected unsuitable soil is encountered below planned subgrade. What should the contractor do to preserve the issue?

Correct Answer

D) Give required notice and document conditions before disturbing evidence.

Differing-site-condition claims typically require prompt notice and documentation.

Answer Options
A
Proceed without notice and claim at final payment
B
Make dispose of all samples immediately the answer for differing site notice
C
Treat the bid bond as notice although the file does not verify differing site notice
D
Give required notice and document conditions before disturbing evidence.

Why This Is the Correct Answer

Differing-site-condition claims typically require prompt notice and documentation.

Why the Other Options Are Wrong

Option A: Proceed without notice and claim at final payment

Choice A (Proceed without notice and claim at final payment.) is rejected because it leaves the work at an informal or incomplete stage, while Differing site notice requires Give required notice and document conditions before disturbing evidence.

Option B: Make dispose of all samples immediately the answer for differing site notice

In procurement and contracting, Dispose of all samples immediately. is the wrong selection for Differing site notice: it leaves out the controlling Differing site notice result: Give required notice and document conditions before disturbing evidence.

Option C: Treat the bid bond as notice although the file does not verify differing site notice

The trap in C is Treat the bid bond as notice. That selection is wrong because it shifts the question into contract administration money flow.

Memory Technique

Pair differing site notice with the real field trigger, then choose the response that produces Give required notice and document conditions before disturbing evidence.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Differing site conditions" to confirm that Differing-site-condition claims typically require prompt notice and documentation.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.