Unexpected unsuitable soil is encountered below planned subgrade. What should the contractor do to preserve the issue?
Correct Answer
D) Give required notice and document conditions before disturbing evidence.
Differing-site-condition claims typically require prompt notice and documentation.
Why This Is the Correct Answer
Differing-site-condition claims typically require prompt notice and documentation.
Why the Other Options Are Wrong
Option A: Proceed without notice and claim at final payment
Choice A (Proceed without notice and claim at final payment.) is rejected because it leaves the work at an informal or incomplete stage, while Differing site notice requires Give required notice and document conditions before disturbing evidence.
Option B: Make dispose of all samples immediately the answer for differing site notice
In procurement and contracting, Dispose of all samples immediately. is the wrong selection for Differing site notice: it leaves out the controlling Differing site notice result: Give required notice and document conditions before disturbing evidence.
Option C: Treat the bid bond as notice although the file does not verify differing site notice
The trap in C is Treat the bid bond as notice. That selection is wrong because it shifts the question into contract administration money flow.
Memory Technique
Pair differing site notice with the real field trigger, then choose the response that produces Give required notice and document conditions before disturbing evidence.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Differing site conditions" to confirm that Differing-site-condition claims typically require prompt notice and documentation.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
