Rock excavation quantities exceed the bid estimate for a unit-price item. What controls payment?

Correct Answer

C) Measured authorized quantity multiplied by the contract unit price, subject to notice terms.

Unit-price payment uses measured quantities under the contract, with required documentation and notice.

Answer Options
A
The original estimated quantity only in all cases
B
Classify it as a verbal daily report with no measurement
C
Measured authorized quantity multiplied by the contract unit price, subject to notice terms.
D
Use the final warranty date as the unit-price overrun notice date

Why This Is the Correct Answer

Unit-price payment uses measured quantities under the contract, with required documentation and notice.

Why the Other Options Are Wrong

Option A: The original estimated quantity only in all cases

The trap in A is The original estimated quantity only in all cases. That selection is wrong because it tries to bypass the Unit price overrun notice checkpoint.

Option B: Classify it as a verbal daily report with no measurement

Choice B gives A verbal daily report with no measurement. Its specific error: it leaves the work at an informal or incomplete stage, while Unit price overrun notice requires Measured authorized quantity multiplied by the contract unit price, subject to notice terms.

Option D: Use the final warranty date as the unit-price overrun notice date

In procurement and contracting, The final warranty date. is the wrong selection for Unit price overrun notice: the option does not produce the required Unit price overrun notice outcome, Measured authorized quantity multiplied by the contract unit price, subject to notice terms.

Memory Technique

Tag the scene with unit price overrun notice: wrong actor or wrong timing means the fix is not Measured authorized quantity multiplied by the contract unit price, subject to notice terms.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Unit-price quantity overrun" to confirm that Unit-price payment uses measured quantities under the contract, with required documentation and notice.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.