NASCLAContractsmedium27% of exam part

A payment reviewer tests the arithmetic: a $194,000 allowance is reconciled to $233,300 actual cost. Before markup, what additive adjustment is due?

Correct Answer

B) $39,300

The calculation gives $39,300 for the stated allowance add. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 348.

Answer Options
A
$35,370
B
$39,300
C
$43,230
D
$49,125

Why This Is the Correct Answer

The calculation gives $39,300 for the stated allowance add.

Why the Other Options Are Wrong

Option A: $35,370

allowance add, choice a: $35,370 is wrong because $35,370 takes one allowance-side amount as the adjustment.

Option C: $43,230

allowance add, choice c: $43,230 takes one allowance-side amount as the adjustment.

Option D: $49,125

allowance add, choice d: $49,125 is wrong because $49,125 takes one allowance-side amount as the adjustment.

Memory Technique

Remember allowance add as "base, adjustment, final unit"; the last unit should read $39,300.

Reference Hint

Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "allowance add calculation" to confirm that The calculation gives $39,300 for the stated allowance add.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.