A field change log shows this condition: which contract document records agreed changes to scope, price, and time?
Correct Answer
B) Change order
Change order is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 304.
Why This Is the Correct Answer
Change order is the controlling requirement
Why the Other Options Are Wrong
Option A: Daily report
In procurement and contracting, Daily report is the wrong selection for Change-order authority: it leaves out the controlling Change-order authority result: Change order.
Option C: Bid tab
Choice C gives Bid tab. Its specific error: it shifts the question into contract administration money flow.
Option D: Unreviewed shop drawing
Choice D (Unreviewed shop drawing) is rejected because it points to Unreviewed shop drawing, but.
Memory Technique
Link change-order authority to its book condition; a different condition means a different answer than Change order.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Change orders" to confirm that Change order is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
