What does a payment bond primarily protect?
Correct Answer
A) Payment claims of covered subcontractors and suppliers.
Payment bonds protect covered lower-tier parties that furnish labor or materials.
Why This Is the Correct Answer
Payment bonds protect covered lower-tier parties that furnish labor or materials.
Why the Other Options Are Wrong
Option B: Apply the owner's property insurance deductible to the payment bond purpose condition
The trap in B is The owner's property insurance deductible. That selection is wrong because the option does not produce the required Payment bond purpose outcome, Payment claims of covered subcontractors and suppliers.
Option C: Apply bid alternates before award to the payment bond purpose condition
Choice C gives Bid alternates before award. Its specific error: it shifts the question into contract administration money flow.
Option D: Apply the contractor's profit margin to the payment bond purpose condition
Choice D (The contractor's profit margin.) is rejected because it answers the Payment bond purpose prompt with the wrong practical move.
Memory Technique
File payment bond purpose under a checkpoint: condition first, number or duty second, answer Payment claims of covered subcontractors and suppliers.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Payment bond" to confirm that Payment bonds protect covered lower-tier parties that furnish labor or materials.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A balloon-framed chase is open from the floor line into the attic, and no blocking has been installed at the concealed transition. What correction is needed before inspection?
Next Question
The stair shop drawing shows a commercial egress stair with wood treads. What minimum tread depth does the IBC generally require?
