A field change log shows this condition: why is a front-loaded schedule of values a payment concern?
Correct Answer
D) It can shift payment ahead of actual earned value
It can shift payment ahead of actual earned value is the correct meaning of front loading in this construction context for concept item 484. Other choices: the distractors describe unrelated administration, payment, or closeout ideas.
Why This Is the Correct Answer
It can shift payment ahead of actual earned value is the correct meaning of front loading in this construction context for concept item 484.
Why the Other Options Are Wrong
Option A: Use front loading to improve record drawings
The trap in A is It improves record drawings. That selection is wrong because it points to It improves record drawings, but.
Option B: Accept the price information as submitted and leave front loading unverified
Choice B gives It deletes retainage. Its specific error: the option tries to substitute, waive, or delete the Front loading control; the item instead requires.
Option C: Use front loading to replace insurance
Choice C (It replaces insurance) is rejected because it removes the controlling Front loading requirement instead of meeting it.
Memory Technique
Keep front loading as a cause-to-effect card with It can shift payment ahead of actual earned value on the back.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "SOV front loading" to confirm that It can shift payment ahead of actual earned value is the correct meaning of front loading in this construction context for concept item 484.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass