Two bidders list alternates differently from the bid form. What should procurement do?
Correct Answer
C) Normalize the comparison to the exact alternate requirements in the instructions.
Alternates must be compared on the basis requested by the bid documents.
Why This Is the Correct Answer
Alternates must be compared on the basis requested by the bid documents.
Why the Other Options Are Wrong
Option A: The bidder should accept the most confusing format
Choice A (Accept the most confusing format.) is rejected because the option does not produce the required Bid alternates comparison outcome, Normalize the comparison to the exact alternate requirements in the instructions.
Option B: Ignore the remaining alternates and price only the lowest one
In procurement and contracting, Ignore all alternates. is the wrong selection for Bid alternates comparison: it tries to bypass the Bid alternates comparison checkpoint.
Option D: Convert alternates to RFIs after award
Choice D gives Convert alternates to RFIs after award. Its specific error: it leaves out the controlling Bid alternates comparison result: Normalize the comparison to the exact alternate requirements in the instructions.
Memory Technique
Picture a closeout folder on the jobsite; bid alternates comparison is solved by the action that leads to Normalize the comparison to the exact alternate requirements in the instructions.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Alternate bid review" to confirm that Alternates must be compared on the basis requested by the bid documents.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?