For a progress-payment cutoff, a foreman is asked verbally to add weekend work, and the contract requires written authorization. What protects payment rights?

Correct Answer

C) Document the direction and follow the change-notice procedure

Document the direction and follow the change-notice procedure is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 374.

Answer Options
A
Do the work silently; without required procurement backup
B
The foreman should hide it in retainage
C
Document the direction and follow the change-notice procedure
D
Apply treat it as warranty to the unauthorized change condition

Why This Is the Correct Answer

Document the direction and follow the change-notice procedure is the contract-appropriate response

Why the Other Options Are Wrong

Option A: Do the work silently; without required procurement backup

Choice A (Do the work silently; without required procurement backup) is rejected because the option delays or omits the controlling step.

Option B: The foreman should hide it in retainage

In procurement and contracting, Hide it in retainage is the wrong selection for Unauthorized change: the action skips the timing, documentation, or field-control step needed for Unauthorized change.

Option D: Apply treat it as warranty to the unauthorized change condition

Choice D gives Treat it as warranty. Its specific error: the choice would not get the project.

Memory Technique

Pair unauthorized change with the real field trigger, then choose the response that produces Document the direction and follow the change-notice procedure.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Change authorization" to confirm that Document the direction and follow the change-notice procedure is the contract-appropriate response

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.