A bidder discovers an addendum was not included in its sealed bid. What is the likely procurement issue?
Correct Answer
C) The bid may be nonresponsive if acknowledgment and pricing were required.
Failure to acknowledge or price required addenda can make a bid nonresponsive.
Why This Is the Correct Answer
Failure to acknowledge or price required addenda can make a bid nonresponsive.
Why the Other Options Are Wrong
Option A: The addendum becomes a warranty item
Choice A gives The addendum becomes a warranty item. Its specific error: the option does not produce the required Late addendum in bid outcome, The bid may be nonresponsive if acknowledgment and pricing were required.
Option B: The owner must ignore all addenda
Choice B (The owner must ignore all addenda.) is rejected because it tries to bypass the Late addendum in bid checkpoint.
Option D: The payment bond cures the omission although the file does not verify late addendum in bid
The trap in D is The payment bond cures the omission. That selection is wrong because it names a financial document or payment mechanism, not the Late addendum in bid action/result stated by The bid may be nonresponsive if acknowledgment and pricing were required.; Required addenda must be acknowledged and included in the bid.
Memory Technique
Picture a pay line on the jobsite; late addendum in bid is solved by the action that leads to The bid may be nonresponsive if acknowledgment and pricing were required.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Addendum omission" to confirm that Failure to acknowledge or price required addenda can make a bid nonresponsive.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass