EstatePass
NASCLAProcurement and Contracting Requirementsmedium

Before backfill begins, a change has $105,750 direct cost with 10 percent overhead and 5 percent profit applied after overhead. What total is proposed?

Correct Answer

C) $122,141

The calculation gives $122,141 for the stated change markup. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 319.

Answer Options
A
$109,926
B
$134,355
C
$122,141
D
$152,676

Why This Is the Correct Answer

The calculation gives $122,141 for the stated change markup. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 319.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.