The construction manager questions a proposed entry: when the instructions call a prebid meeting mandatory, what is the bid risk of nonattendance?
Correct Answer
B) The bid may be rejected as nonresponsive under the instructions
The bid may be rejected as nonresponsive under the instructions is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 231.
Why This Is the Correct Answer
The bid may be rejected as nonresponsive under the instructions is the controlling requirement
Why the Other Options Are Wrong
Option A: The bid automatically receives a bonus
Choice A gives The bid automatically receives a bonus. Its specific error: it shifts the question into contract administration money flow.
Option C: Make attendance becomes optional after award the answer for prebid meeting
In procurement and contracting, Attendance becomes optional after award is the wrong selection for Prebid meeting: it points to Attendance becomes optional after award, but.
Option D: Apply the project scope is deleted to the prebid meeting condition
The trap in D is The project scope is deleted. That selection is wrong because it removes the controlling Prebid meeting requirement instead of meeting it.
Memory Technique
Treat prebid meeting like a labeled shelf; only the matching condition belongs with The bid may be rejected as nonresponsive under the instructions.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - prebid procedures / substitutions / protests to confirm that The bid may be rejected as nonresponsive under the instructions is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
