The safety manager verifies a construction-standard value: which term describes a bid that materially follows the bid form, addenda, security, and other bidding requirements?
Correct Answer
A) Responsive bid
Responsive bid is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 209.
Why This Is the Correct Answer
Responsive bid is the controlling requirement
Why the Other Options Are Wrong
Option B: Responsible bidder
The trap in B is Responsible bidder. That selection is wrong because the option answers a paperwork, payment, or bonding issue.
Option C: Unit-price underrun
Choice C gives Unit-price underrun. Its specific error: it leaves out the controlling Responsive bid result: Responsive bid.
Option D: Substantial completion
Choice D (Substantial completion) is rejected because the choice would not get the project to Responsive bid, which is the Responsive bid result verified by the source. The cited answer is Responsive bid.
Memory Technique
Link responsive bid to its book condition; a different condition means a different answer than Responsive bid.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bid responsiveness" to confirm that Responsive bid is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?