NASCLAProcurement and Contracting Requirementsmedium

Bid documents include addenda issued before bid day. What bid-form action is normally required?

Correct Answer

A) Acknowledge the addenda and include their scope in the bid.

Addenda revise bidding documents and normally must be acknowledged in the bid.

Answer Options
A
Acknowledge the addenda and include their scope in the bid.
B
The contractor should ignore addenda until after award
C
The contractor should price addenda only as change orders
D
The contractor should attach them only to the final pay application

Why This Is the Correct Answer

Addenda revise bidding documents and normally must be acknowledged in the bid.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.