A payment reviewer tests the arithmetic: what is the purpose of an RFI when contract documents conflict?
Correct Answer
A) Request clarification before proceeding with affected work
Request clarification before proceeding with affected work is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 132.
Why This Is the Correct Answer
Request clarification before proceeding with affected work is the controlling requirement
Why the Other Options Are Wrong
Option B: The reviewer should approve a substitution automatically
Choice B gives Approve a substitution automatically. Its specific error: the option does not produce the required RFI outcome.
Option C: Handle rFI by choosing to waive contract time
Choice C (Waive contract time) is rejected because it treats RFI as optional.
Option D: Apply release retainage to the rFI condition
In procurement and contracting, Release retainage is the wrong selection for RFI: the option answers a paperwork, payment, or bonding issue.
Memory Technique
File RFI under a closeout folder: condition first, number or duty second, answer Request clarification before proceeding with affected work.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Requests for information" to confirm that Request clarification before proceeding with affected work is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass