The construction manager questions a proposed entry: a low proposal excludes temporary heat that the specifications assign to that trade. What should be done before award?

Correct Answer

D) Close the scope gap or carry the missing cost in the correct package

Close the scope gap or carry the missing cost in the correct package is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 411.

Answer Options
A
Hope another trade includes it; without contract authorization
B
The contractor should delete the specified heat
C
The contractor should wait for final payment
D
Close the scope gap or carry the missing cost in the correct package

Why This Is the Correct Answer

Close the scope gap or carry the missing cost in the correct package is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 411.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.