The construction manager questions a proposed entry: a low proposal excludes temporary heat that the specifications assign to that trade. What should be done before award?
Correct Answer
D) Close the scope gap or carry the missing cost in the correct package
Close the scope gap or carry the missing cost in the correct package is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 411.
Why This Is the Correct Answer
Close the scope gap or carry the missing cost in the correct package is the contract-appropriate response
Why the Other Options Are Wrong
Option A: Hope another trade includes it; without contract authorization
Choice A (Hope another trade includes it; without contract authorization) is rejected because it tries to bypass the Bid scope gap checkpoint.
Option B: The contractor should delete the specified heat
In procurement and contracting, Delete the specified heat is the wrong selection for Bid scope gap: it treats Bid scope gap as optional.
Option C: The contractor should wait for final payment
The trap in C is Wait for final payment. That selection is wrong because the option delays or omits the controlling step.
Memory Technique
Remember bid scope gap by its jobsite consequence: the correct move points to Close the scope gap or carry the missing cost in the correct package.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Buyout scope review" to confirm that Close the scope gap or carry the missing cost in the correct package is the contract-appropriate response
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass