The stormwater inspector walks the site and notes this item: a cheaper product differs from the specified basis and has not been approved. What should happen before purchase?
Correct Answer
C) Submit it through the substitution procedure and wait for approval
Submit it through the substitution procedure and wait for approval is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 356.
Why This Is the Correct Answer
Submit it through the substitution procedure and wait for approval is the contract-appropriate response
Why the Other Options Are Wrong
Option A: The contractor should install first
Choice A gives Install first. Its specific error: it leaves out the controlling Substitution result.
Option B: Base the substitution response on mark it as an RFI
Choice B (Mark it as an RFI only) is rejected because it leaves the work at an informal or incomplete stage, while Substitution requires.
Option D: The contractor should delete the product
The trap in D is Delete the product. That selection is wrong because the option tries to substitute, waive, or delete the Substitution control; the item instead requires.
Memory Technique
Remember substitution by its jobsite consequence: the correct move points to Submit it through the substitution procedure and wait for approval.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Substitution procedure" to confirm that Submit it through the substitution procedure and wait for approval is the contract-appropriate response
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass