A roofing foreman checks the substrate condition: a low proposal excludes temporary heat that the specifications assign to that trade. What should be done before award?
Correct Answer
C) Close the scope gap or carry the missing cost in the correct package
Close the scope gap or carry the missing cost in the correct package is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 323.
Why This Is the Correct Answer
Close the scope gap or carry the missing cost in the correct package is the contract-appropriate response
Why the Other Options Are Wrong
Option A: Base the bid scope gap response on hope another trade includes it
Choice A (Hope another trade includes it) is rejected because it points to Hope another trade includes it, but.
Option B: The foreman should delete the specified heat
In procurement and contracting, Delete the specified heat is the wrong selection for Bid scope gap: the option tries to substitute, waive, or delete the Bid scope gap control; the item instead requires.
Option D: The foreman should wait for final payment, leaving bid scope gap unverified
Choice D gives Wait for final payment. Its specific error: it tries to bypass the Bid scope gap checkpoint.
Memory Technique
Picture a anchor on the jobsite; bid scope gap is solved by the action that leads to Close the scope gap or carry the missing cost in the correct package.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Buyout scope review" to confirm that Close the scope gap or carry the missing cost in the correct package is the contract-appropriate response
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass