After the revised drawing is issued, approved work to date is $2,029,500; retainage is 10 percent and prior payments are $1,043,000. What current payment is due?
Correct Answer
A) $783,550
The calculation gives $783,550 for the stated current payment. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 301.
Why This Is the Correct Answer
The calculation gives $783,550 for the stated current payment.
Why the Other Options Are Wrong
Option B: $705,195
current payment, choice a: $705,195 omits a required add-on/subtraction; the numeric gap is $78,355.
Option C: $861,905
current payment, choice b: $861,905 adds an extra unstated add-on/subtraction; the numeric gap is $78,355.
Option D: $979,437
current payment, choice d: $979,437 backs into 0.48 when divided by $2,029,500; the accepted setup gives 0.39 on that same base.
Memory Technique
Store current payment with its last math move; nearby answers are usually unfinished versions of $783,550.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "current payment calculation" to confirm that The calculation gives $783,550 for the stated current payment.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
